Website Rebuild Workflow: pre-read
For the 90-minute working session (Dakota, Amy, Wyatt, Don Clark, Jenn, Kelly, Jayme, Korinne). Prepared 2026-10-05 from sga3p task history, the SharePoint trackers, meeting transcripts, and a read-only check of the current platform build. Updated 2026-10-06 with Amy's proposed pilot list, standardized workflow (now including the Korinne/Wyatt access step and the Growth Manager content-collection step), role questions, asset governance notes, and a pilot readiness audit against all seven candidates (§6). Full documents, checklists, and evidence sit in data/output/website-rebuild-workflow/.
1. What the evidence says
The written process exists
Prioritization model with Gate A and Gate B (validated on 17 practices), a 5-day launch playbook, a post-launch KPI framework, DS-210, the rebrand owner split, the GD-011 access guide, the GP sitemap spec, and the sga3p conventions.
None of it ran the MSP builds
Sites entered from a 17-row list with one-line reasons. The tracker's approval columns were never filled. Status lived in sga3p comments, Teams, email, and screenshot workbooks. The approval sequence was restated at least 12 times and never settled.
Where the time went
8–39 days to first feedback
Valdosta took 70 days and Oakwood 67 from draft to pre-launch. Two sites are stuck on domain transfer after approval. MSP check-ins were weekly throughout.
The platform works
Bell Dental went from site record (9/22) to live (by 10/2) with 190 URLs, 193 verified redirects, GTM, a Jotform, sitemap, robots, and four legal pages. No sga3p task tracked it, and it launched without a booking link.
The six patterns that cost the most
| Pattern | Example | Change proposed |
|---|---|---|
| Build before access | Lake Mary down during a registrar transfer after launch; Rene Roberts and North River "Pending Domain"; "Open MSP access to all SGA sites" open 77 days | Access checklist is an entry condition for assignment; registrar register per practice |
| Review latency | Bright Smiles: "It's been two weeks since I passed over this draft" (MSP, 8/13); Kingston 39 days with no feedback | One Growth Manager-owned consolidated review, 5 business days, one round |
| Unverified content | "The official practice name is Dr. Steven Hochfelder D.M.D. P.A." (9/9); doctors on a draft who had left the practice | Verified practice record is a build input; the builder never treats the old site as truth |
| Missing photos | Valdosta: no photos, iStock fallback debated; DHG shoot cancelled after six reschedules | Photo decision at verification with fallback rules; shoot booked at T-30 |
| Unrecorded pauses | Valdosta paused 8/13 via Teams; "I wasn't aware we were paused" (9/15); Little Smiles Blocked since 7/30 with no reason | Every hold carries a reason, owner, and review date on the task |
| No launch approver | "I don't know who gives the approval to launch" (9/11); MSP said the okay used to come from Don | One named approver, with Gate evidence in fixed comment formats |
What worked (keep it)
- Structured office review by the Growth Manager (Lake Mary: three waves of edits, cleared in 3 days once run).
- Default-forward rule (SCO: "If no response by 9/30, will move forward with publishing").
- Logins posted in the task, launch the same day (Rockaway, Mid-Pen).
- Doctor interviews with transcript and brand voice attached (Bell, Beaches, SCO).
2. The proposed workflow
One flat sga3p task per stage per site, chained with blocked-by links. Owners and service levels are proposals.
| # | Stage | Owner | Gate to exit | SLA (proposal) |
|---|---|---|---|---|
| 0 | Platform readiness (once) | Dakota, Don Clark | Written answers: preview URL, editor access, deploy trigger, draft-site gating, and the cutover plan from the interim stack | Before any non-pilot assignment |
| 1 | Intake | Growth Manager | All required fields, evidence, proposed category | Acknowledge in 1 business day |
| 2 | Scoring and queue decision | Dakota (Amy co-approves) | Decision written on the task; bucket set | Weekly review |
| 3 | Verification: Gate A, Gate B, access, content, photo decision | Growth Manager (Wyatt on access) | GATE A PASSED and GATE B PASSED comments; access checklist verified | 15 business days; items expire at 30 days |
| 4 | Ready for assignment and acceptance | Dakota approves; Don accepts | Handoff package attached; "ACCEPTED, commit date" comment | Accept within 2 business days |
| 5 | Build | Don Clark (Wyatt sets up tracking, forms, redirects in parallel) | Preview URL posted | Commit inside 15 business days for a standard site |
| 6 | Internal QA | Growth Manager consolidates; Wyatt technical, Studio brand, Dakota content | QA COMPLETE; two rounds included | 3 business days |
| 7 | Practice sign-off | Growth Manager with OM and doctor | PRACTICE SIGN-OFF or default-forward with ROD notice | 5 business days |
| 8 | Launch approval | Named approver (D1) | Pre-launch checklist attached; GO recorded; baseline captured | 2 business days |
| 9 | Cutover | Don deploys; Wyatt DNS; Korinne GBP | Day 1 smoke within 24 hours | Tuesday to Thursday |
| 10 | Post-launch and transition | Wyatt Day 7; Growth Manager Day 30 to 90 | Day 30 audit baseline and KPI review | Documented KPI cadence |
Who approves what
- Doctor: clinical accuracy of bios and service pages, in writing. Not design, brand, or hours.
- Office Manager: business facts (name, address, phone, hours, insurance, roster, booking vendor).
- The Studio: brand, only when the brand or design changes.
- Growth Manager, then Dakota: content strategy and copy.
- Wyatt: technical readiness. ROD: Gate A. One approver: go or hold.
3. Decisions for the session
| ID | Decision | Options |
|---|---|---|
| D0 | Cutover plan and date from the interim Sanity-backed stack (Bell Dental live, Artistry draft) to Don Clark's custom headless CMS; do new builds start on the custom CMS or the interim stack? | Custom CMS only from a named date; interim stack until the CMS ships, then migrate; case by case |
| D1 | Single launch approver | Dakota; Amy; Growth Manager with Dakota as backstop |
| D2 | Queue order and displacement authority | Dakota with Amy co-approving; the weekly review as a body |
| D3 | Content bar at launch | Hide unverified pages and launch; launch what was already live; no launch without a page-by-page read |
| D4 | Who signs content | Doctor clinical and OM facts; doctor everything |
| D5 | Default-forward rule | 5 days with two reminders and ROD notice; 10 days; reject |
| D6 | Wyatt's rebuild role | Technical owner and QA, not builder; also builds overflow |
| D7 | Don's WIP limit and acceptance SLA | 3 in build, 3 in review, accept in 2 business days; other numbers |
| D8 | Photography fallback policy and Dawson rate card | Adopt; amend |
| D9 | Registrar and DNS register owner; GoDaddy account of record | Wyatt builds and Dakota owns; IT; Brooke |
| D10 | sga3p project | Reuse website-rebuild-sop renamed; new project |
| D11 | How the 10-task set is created | Rebuilt New Website template; script |
| D12 | Pilot site and T0 | Clay Center (recommended; Gate A must be confirmed because it is flagged as a divest or Advanced Care candidate); Rock Hotel Dental (alternate); AID (platform proof, not the process pilot) |
| D13 | MSP sites in flight | Apply stages 7 to 10 now with Wyatt as technical owner; cancel Schramm (divested); write the Little Smiles reason or cancel |
| D14 | Practice-side validation call | Pilot practice ROD, OM, doctor within a week |
| D15 | Blog URL pattern and multi-location support | Ask Don for dates now, before Peak, Cassity, or AID are scheduled |
4. Agenda (90 minutes)
| Time | Item | Lead |
|---|---|---|
| 0:00 | Purpose and ground rules | Dakota |
| 0:05 | Findings: cohorts, six patterns, what worked | Amy |
| 0:20 | D0 cutover plan and D1 approver | Dakota |
| 0:30 | Walk the ten stages with Bell Dental as the retrospective | Amy and Don Clark |
| 0:50 | Roles and service levels: each role answers its questions | Each role |
| 1:05 | sga3p structure and the pilot; assign configuration actions | Dakota |
| 1:20 | Decision log read-back, action items, next review date | Dakota |
5. Pilot and rollout (proposal)
Pilot: Clay Center (LocalIQ migration order #2, single location, SGA already holds admin access, 42 pages, no blog, 82 redirects to test, domain safe to 2027). Target launch Thursday 2026-11-12, retrospective 2026-11-20. Alternate: Rock Hotel Dental. Artistry in Dentistry continues as the platform proof (blog path, video block, form and tracking fields).
Before the session: renew peakfamilydentalaz.com and list the other domains expiring before 2027-03-31 with account holders; Don's written answers to the platform questions and the cutover plan; set Don up as an sga3p guest and confirm his contract state; cancel Schramm; write the Little Smiles reason; correct sga3p manager fields.
After the pilot: LocalIQ sites in expiry and readiness order (Portage, Apache or Daybreak, Heritage, Cavendish, Florence; Peak and Cassity after multi-location support); MSP leftovers stay in Wyatt's launch lane; new requests only through intake.
6. Pilot list and open questions (Amy, 2026-10-06)
Candidate groupings for the working session. Readiness, complexity, and phase order are open — team input requested below.
Proposed pilot candidates (single location)
| # | Practice | Domain | Notes |
|---|---|---|---|
| 1 | Richmond Hill Family Dentistry | richmondhillfamilydentistry.com | Doctor interview completed. SGA no longer owns richmondhillcosmeticdentistry.com or has access to its content — heavier content lift. |
| 2 | Sumter Dentistry | sumterdentistry.com | Doctor interview completed. |
| 3 | Eric Moskowitz | ericmoskowitzdds.com | |
| 4 | Southern Oak Conway | southernoakconway.com | |
| 5 | Jonesville Dentistry | jonesvilledentistry.com | |
| 6 | Wirtz Dentistry | wirtzdentistry.com | |
| 7 | Central Florida Perio | centralfloridaperio.com |
Pilot readiness audit (as of 2026-10-06)
Gates checked against the updated workflow: doctor interview on file (VideoAsk + Practice Knowledge Base entry), gap questionnaire written, brand design package complete, website audit within the 30-day window, OM confirmation of practice facts in the snapshot, asset location confirmed, and access (GoDaddy, CMS, social) confirmed by Korinne / Wyatt.
| # | Practice | Interview | PKB | Audit | Brand pack | Gap questionnaire | OM snapshot | Assets | Access | Ready for Don? |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Richmond Hill Family Dentistry | Yes — Dr. Martinolas, 2026-10-05 (VideoAsk) | Yes | Yes 2026-09-09 | Yes | Yes — richmond-hill-sitemap-questionnaire-2026-10-06.docx | No | No — Jenn to confirm; Dawson shoot likely | No | Not yet. Heavy content lift from lost richmondhillcosmeticdentistry.com; needs OM facts, access, assets; Jenn flags that VideoAsk alone may not be enough |
| 2 | Sumter / Restorative Arts Dental | Yes — Dr. GE Rabon, 2026-09-17 (VideoAsk) | Yes | Yes 2026-09-09 | Yes | Yes — restorative-arts-sumter-sitemap-questionnaire-2026-10-06.docx | No | No — Jayme to locate | No | Closest. Still not. Only OM snapshot, Jayme asset locate, and access remain — all this-week items. Recommended T0 pilot |
| 3 | Eric Moskowitz | No | No | Yes 2026-09-09 | Partial — folder is Moskowitz-Cosmetic-Implant-&-General-TBD; logo + BRAND.md only, no voice | No | No | No | No | Not ready. Amy's "Kelly has everything" refers to brand; voice and content gates are open |
| 4 | Southern Oak Conway | No | No (Greenville and Simpsonville have PKB entries; Conway does not) | Yes 2026-09-09 | No — no claude-design-package for Conway | No | No | No | No | Not ready. Brand, interview, PKB, questionnaire all missing |
| 5 | Jonesville Dentistry | No | No | Yes 2026-09-09 | Yes | No | No | No | No | Not ready. Brand pack only; VideoAsk and gap check still owed |
| 6 | Wirtz Dentistry | No | No | Yes 2026-09-09 (Wirtz Jackson) | Yes | No | No | No | No | Not ready. Brand pack only |
| 7 | Central Florida Perio | No | No | Yes 2026-09-09 | Yes | No | No | No | No | Not ready. Brand pack only |
Multi-location — include in pilot or hold for next phase (depends on D15)
| Practice | Domain | Locations |
|---|---|---|
| OBX Perio & Implant | obxperioimplant.com | 2 |
| Chattahoochee Valley Dental | chattahoocheevalleydental.com | 2 |
| LC Perio | lcperio.com | 3 |
Needs a broader branding and structure discussion
- El Paso Gum Surgery + Las Cruces Gum Surgery —
elpasogumsurgery.comandlascrucesgumsurgery.com. - Amelia Perio + Beaches Periodontics —
ameliaperio.comandbeachesperiodontics.com. Previously discussed combining into one site; direction must be resolved before building. - My Dental Partners —
mydentalpartners.com. 18 locations on a main hub with individual sites; overall structure must be agreed.
Dakota and Amy will take these three groups in a separate session.
Standardized workflow Amy is proposing for every rebuild
Bell is the starting point: Kelly interviewed Dr. Bell and Dr. Matkins, their voice and practice details are in the sga3p Practice Knowledge Base, and Claude compared the interviews against the live site and Don's new build to generate a gap-only questionnaire (attached to the note).
| # | Step | Owner / Tool |
|---|---|---|
| 1 | Access confirmed to deploy a new site: GoDaddy, current CMS, social profile links | Korinne + Wyatt |
| 2 | Doctor interviews via the VideoAsk link, added to the Practice Knowledge Base | Doctors (prompted by Growth Manager) |
| 3 | Content gap review: Claude compares interviews to the live site and, when available, the new build | Claude (via Practice Knowledge Base in sga3p MCP) |
| 4 | Practice-fact confirmation (hours, address, phone, doctors) in the practice snapshot (draft; feeds Yext and website). Separate questionnaire covers content only. | Office Manager |
| 5 | Content and assets: OM helps close the content gaps and works with a photographer if needed | Office Manager |
| 6 | Growth Manager reviews all content and copy gaps and schedules any interview needed to close them | Growth Manager |
| 7 | QA and launch (final approver agreed before launch — see D1) | Wyatt + named approver |
| 8 | Task tracking: one parent task in sga3p per rebuild with steps, owners, and handoffs underneath | sga3p (shape still open — see D10/D11) |
Note: step 6 ("one parent task with steps under it") is Amy's proposal; it is in tension with the flat-task-per-stage approach in §2. D10 and D11 are the decisions that settle this.
Role-specific questions to answer before or during the session
| Role | Question |
|---|---|
| Mike | Which of the sites above have usable assets in Frame.io? Flag any that need an image plan. |
| Don | What do you need in a complete handoff before you can start? If Richmond Hill is first, what is the next step and what is missing? |
| Wyatt | Does this workflow match how you want to receive and QA work? Flag anything you would change. |
| Jenn | Does Richmond Hill have usable photos and other assets? If not, coordinate a Dawson shoot (local to Richmond Hill) after ROD/OM approval. |
| Jayme | Locate the Sumter assets and confirm where they are stored. |
Assets and storage — needs confirming this week
Working assumption: Frame.io is the master photo/video library; the sga3p Brand Index holds logos and colors. Open questions for the session:
- Where should Don and Wyatt pull assets from when building a site?
- Where do new office photos go after a shoot?
- What is the "Locations" folder for?
With Mike leaving, these need to be clearly documented this week.
Decisions this session should leave with
- Agreed pilot list and starting order.
- Clear content-to-build handoff.
- Confirmed asset locations.
- Standard sga3p task template with owners and approval steps.
7. Files
01-assessment-msp-lessons.md: assessment and the 23-row evidence table with task links02-intake-and-prioritization.md: who can request, rebuild versus targeted fixes, intake fields, rubric, urgent handling, ready checklist03-workflow-raci-and-don-assignment.md: roles, approvals, stages, SLAs, handoff package, pre-launch checks, rollback, monitoring04-photography-and-video.md: minimums, shoot triggers, shot list, fallbacks05-sga3p-task-structure.md: the 10-task set, fields, statuses, approval comment formats, views, configure-now versus development06-team-working-session.md: agenda, decisions, role questions, Bell Dental walkthrough, templates07-rollout-plan.md: pre-session actions, pilot timeline, adoption order, measuresSGA-Website-Rebuild-Checklists.xlsx: eleven tabs including the access and asset checklist, Don handoff package, pre-launch checklist, decision log, action items, task set templateevidence/: sga3p task pull (158 classified tasks), document inventory, platform readiness, meeting evidence (493 dated items), direct probes
Labels used throughout: Documented (existing SGA policy), Observed (seen in sga3p, workbooks, or transcripts), Proposal (for agreement), Inference (our reading where no source states it). Nothing in this pre-read records a decision as made.